Given below is a WBS of a project.
| Activity | Activity time in days | Immediate Predecessors |
| a | 30 | -- |
| b | 20 | -- |
| c | 15 | a |
| d | 18 | b |
| e | 32 | b |
| f | 25 | c, d |
| g | 22 | c, d |
| h | 17 | e, g |
| i | 8 | e |
| j | 15 | i |
Draw an activity network diagram for this project and find the critical path by finding earliest time and latest time of various events. What is the project completion time?